# 数据中心资源披露 / Data-centre resource disclosure

- 位置、流域、年度及旱季 / Location, basin, year and dry season
- 平均与峰值IT负荷、设施购电、PUE边界 / Average and peak IT load, facility purchases and PUE boundary
- 取水和消耗分别报告，现场和发电侧分开 / Report withdrawal and consumption separately; separate site and generation
- WUE分母、时间、水源、供电排放与水因子 / WUE denominator, period, source and power emission/water factors
- 接入投资、谁付费、退出责任、应急方案 / Connection investment, payer, exit responsibility and contingency

模型：IT kWh=MW×1000×hours；facility=IT×PUE；现场升=IT×WUE；发电侧升=facility×grid factor。
Model: same equations; only add non-overlapping consumption boundaries.
演示非许可、非每次AI调用足迹。Illustration, not a permit or per-query footprint.